Payment After Punch List

1 MIN READ

When exactly is a punch list finished? At the Orren Pickell Remodeling Group in Chicago, conflicting answers to that question have led some clients to withhold the final 5% of their payments. “You might have a customer withholding payment because of a window crank that was back-ordered,” says Lisa Pickell, the company’s remodeling group manager. “On a $1 million project, that’s a $50,000 window crank.”

To head off such disputes, Orren Pickell restructured its draw schedule. Contracts now call for the last payment of 20% at final inspection rather than 15% at final inspection and 5% at the completion of the punch list. The company will also insert a holdback clause in the contract or negotiate a reasonable holdback at the client’s request. “That way you look like you’re doing them a favor,” Pickell says.

Fewer draws reduce the company’s receivables, which helps improve loan terms. Pickell says the restructured draw schedule is not about simply collecting money —it is part of a broader effort to change customer perceptions about the close of a job. The company also introduces a polished, service-oriented maintenance crew at final inspection. Pickell hopes this step will create a sense of closure for the homeowner, signaling that the job is finished and that punch list items should be considered regular maintenance rather than the final stage of the project.

About the Author

No recommended contents to display.